web analytics

The Children’s Center at the Bridge Over Troubled Waters

Pasadena, TX (Harris Co.)

Work will consist of The Children’s Center at the Bridge Over Troubled Waters in the City of Pasadena. Project will include the demolition of the existing elementary school buildings and associated site improvements; as well as the construction of a new, 2-story approximately 25,000 sf elementary school and all related site facilities. Project scope will include¬†new work consisting of earthwork, concrete foundations and floor slabs, structural steel framing, PVC single ply roofing, CMU masonry and light gauge steel framed exterior walls, cementitious panel veneer, plaster, hollow metal doors and frames, aluminum and glass doors and frames, solid core plastic laminate doors, door hardware and access control system / devices, interior and exterior glazing, CMU and drywall interior partitions, suspended acoustical and gypsum board ceilings, interior finishes, specialties and equipment, and food service equipment and fixtures; new site-work consisting of rough and final grading, imported select fill, concrete paving and sidewalks, underground storm, water and sanitary utilities, fencing, landscaping and irrigation system, and aluminum walkway covers; and the MEP work consisting of HVAC systems, plumbing, electrical power and lighting fixtures, communication systems, data infrastructure and wiring, automatic fire sprinkler system, as well as fire alarm and security systems.

 


CONSTRUCTION CATEGORIES BIDDING THIS PROJECT:

Architect – 1
Bidding General Contractor – 14
Civil Engineer – 1
Communications – 1
Concrete – 1
Heating, Ventilation & A/C – 1

PROJECT DOCUMENTS ON THIS PROJECT:

BLUEPRINTS
Architectural – 30 sheets
Architectural Site – 4 sheets
Civil – 21 sheets
Electrical – 9 sheets
Electrical and Plumbing – 1 sheets
General – 5 sheets
Landscape – 1 sheets
Mechanical – 6 sheets
Plumbing – 9 sheets
Structural – 12 sheets
Technology – 3 sheets

SPECIFICATIONS
24 Sections

ADDENDA
8 Reported

MEMOS
53 Reported


First Reported on Thursday, June 25, 2020 – Last Updated 7/10/2020 3:20:09 PM

Project Information
PROJECT ID: 2020-4C53
BID DATE/TIME: 7/14/2020
02:00pm CST
EST. COST: $4,500,000
SQ FOOTAGE: 25000
STATUS: Bidders List / Update
PROJECT TYPE: New Construction
CATEGORY: Education
PUBLIC FUNDING: Yes
NON-MEMBER? LEARN MORE MEMBERS CLICK HERE TO ACCESS NOW!
VBX first reported in the Virtual Plan Room on Thursday, June 25, 2020.
Members with access to this service may monitor progress by tracking Project ID #2020-4C53.
Construction Preview
By |2020-07-13T12:11:10-05:00July 14th, 2020|Bid Bulletin|

About the Author:

Leave A Comment