Null Middle School Additions and Renovations – Sheldon ISD

Houston, TX (Harris Co.) 

Work includes a new two-story addition to an existing middle school, approximately 43,270 SF, and select interior renovations of existing rooms. New rooms in the addition include classrooms, science laboratories, administration rooms, and building function rooms (mechanical, electrical, etc.). The work may also include the following;
1. Tree protection, site utilities, cement concrete paving
2. Foundation
3. Structural frame
4. Metal fabrications
5. Face brick veneer
6. Metal wall panels
7. Aluminum, glass and window wall
8. PVC Roofing
9. Interior walls
10. Tile, resilient flooring, sheet carpeting, resinous athletic flooring
11. Suspended plaster, suspended drywall, lay-in panels, sound absorbing units
12. Steel doors and frames, wood doors, Kynar coated storefront, overhead coiling doors
13. Casework
14. Specialties
15. Hydraulic elevators
16. Automatic sprinkler system
17. Plumbing systems
18. HVAC Systems and building automation system
19. Electrical, telecommunications systems, telephone systems, lightning protection and emergency power
20. Fire detection, alarm and emergency call systems

 


CONSTRUCTION CATEGORIES BIDDING THIS PROJECT:

Architect – 1
Bidding General Contractor – 3
Civil Engineer – 1
Electrical – 1
Integrated Ceiling Assemblies – 1

PROJECT DOCUMENTS ON THIS PROJECT:

BLUEPRINTS
Architectural – 66 sheets
Architectural Demolition – 3 sheets
Architectural Site – 2 sheets
Architectural Site Demolition – 2 sheets
Civil – 16 sheets
Electrical – 16 sheets
Fire Protection – 3 sheets
General – 15 sheets
Mechanical – 15 sheets
Plumbing – 14 sheets
Structural – 18 sheets
Technology – 9 sheets

SPECIFICATIONS
24 Sections

ADDENDA
1 Reported

MEMOS
0 Reported


First Reported on Thursday, May 11, 2023 – Last Updated 5/23/2023 9:12:37 AM


Project Information
PROJECT ID: 2023-382C
BID DATE/TIME: 5/25/2023
01:00pm CST
EST. COST: $14,000,000 – $20,000,000
SQ FOOTAGE: 43270
STATUS: Project Update
PROJECT TYPE: Additions / Renovations / Upgrade
CATEGORY: Education
PUBLIC FUNDING: Yes
NON-MEMBER? LEARN MORE MEMBERS CLICK HERE TO ACCESS NOW!
VBX first reported in the Virtual Plan Room on Thursday, May 11, 2023.
Members with access to this service may monitor progress by tracking Project ID #2023-382C.
Construction Preview
By |2023-05-24T11:33:10-05:00May 25th, 2023|Bid Bulletin|

About the Author: