Ovilla, TX (Ellis Co.) –
Scope of work consists of package 3 for the new construction of the Middle School #2, approximately 184,898 sq ft.
Work includes masonry, drywall, interior finishes, specialties, food service, MEP systems, landscaping, sports fields, and bleachers.
Proposals need to be broken out between school, site, and off-site.
At this point in time, earthwork, utilities, concrete, steel fab/erect, and switchgear procurement have already been awarded in earlier bid packages.
CONSTRUCTION CATEGORIES BIDDING THIS PROJECT:
Architect – 2
Construction Manager – 1
Fences & Gates – 1
Integrated Ceiling Assemblies – 1
Landscape Architect – 1 |
|
PROJECT DOCUMENTS ON THIS PROJECT:
BLUEPRINTS
Architectural – 105 sheets
Electrical – 52 sheets
Fire Protection – 3 sheets
Food Service – 13 sheets
General – 5 sheets
Landscape – 22 sheets
Mechanical – 16 sheets
Plumbing – 18 sheets
Reference – 2 sheets
Roofing – 15 sheets
SPECIFICATIONS
25 Sections |
ADDENDA
10 Reported
MEMOS
2 Reported |